Data Centers in Ohio: How Many, Where and What It Costs (2026)

AmaraBy Amara|Updated 9 November 2026
A glowing outline of Ohio at night with a bright cluster of light in the center and thin power lines running outward

Key Numbers

166
Operating Ohio data centers in February 2026, plus 57 more planned, under construction or land-banked
Pew Research Center, from DataCenterMap, Feb 19, 2026
278
Ohio data center buildings tracked in all stages, fourth most in the US
Cleanview, Nov 8, 2026
17,861 MW
Data center projects under contract with AEP Ohio, 5,642 MW of it signed under the new tariff
AEP Ohio update to PUCO, Feb 12, 2026
$1.57B
State sales tax revenue Ohio gave up on data centers in 2025, about 11 times the $136 million forecast
Ohio Department of Taxation, May 2026
21 of 41
Local data center ballot measures in the US on Nov 3, 2026 that were in Ohio, with bans or limits passing in at least 14 towns (unofficial)
Media tallies, Nov 2026

Key Takeaways

  • 1Ohio had 166 operating data centers in February 2026 and 278 buildings tracked in all stages by November. Its 2023 electricity use was only 2.4 TWh, 1.58% of the state total, so Ohio is a pipeline state, not yet a big consumer.
  • 2AEP Ohio has 17,861 MW of data center projects under contract, about 1.7 to 2.2 times the utility's entire recent peak demand of 8,000 to 10,500 MW. A tariff approved in July 2025 makes new loads above 25 MW pay for at least 85% of their subscribed power.
  • 3Ohio is where the backlash has gone furthest: Governor DeWine paused new tax-break applications in May 2026, and voters in at least 14 towns approved data center bans or limits on November 3, 2026, while OpenAI plans an 8 GW campus in Pike County.

Ohio has about 166 operating data centers, and 278 buildings tracked in all stages as of November 2026. That makes it the fourth-largest state by tracked buildings, behind Virginia, Texas and Pennsylvania. Pew Research Center, using DataCenterMap, counted 223 in February 2026: 166 operating and 57 planned, under construction or land-banked.

What Ohio has built so far is much smaller than what it has signed up for. EPRI estimated Ohio data centers used just 2.4 TWh of electricity in 2023, or 1.58% of the state's power. Meanwhile AEP Ohio, the state's largest utility, has 17,861 megawatts of data center projects under contract. That is roughly twice the utility's entire peak demand.

Below you will find the counts by tracker, where the buildings cluster, what the AEP Ohio contracts and tariff mean, what the state's tax break cost in 2025, and how voters and the governor pushed back in 2026.

How Many Data Centers Are in Ohio? 166 Operating, 278 Tracked

Ohio has about 166 operating data centers and 278 tracked in all stages, depending on the tracker and the date.

SourceDateOhio figureWhat it counts
Pew Research Center, from DataCenterMapFeb 19, 2026223 total166 operating plus 57 planned, under construction or land-banked
CleanviewNov 8, 2026278Operating, under construction and planned buildings

The gap between 223 and 278 reflects pipeline growth between February and November and a difference in method: DataCenterMap is a directory of listed facilities, and Cleanview builds its list from public records and counts individual buildings.

Ohio looks different from the two states closest to it in building count:

StateTracked buildings (Cleanview, Nov 2026)Data center electricity, 2023 (EPRI)Share of state electricity
Pennsylvania3004.6 TWh3.16%
Ohio2782.4 TWh1.58%
Georgia2516.2 TWh4.26%

The count matters less than what each building draws. EPRI estimated that Ohio's data centers used 2.4 TWh in 2023, which is 1.58% of the state's electricity and far below Virginia's 25.59%. In EPRI's 2030 scenarios the share rises to between roughly 1.9% and 3.8%. Ohio ranks fourth in building count but falls outside EPRI's top 15 states for power use, which shows how much of its pipeline had not been built by 2023. We explain that gap in our ranking of data centers by state.

Where Ohio's Data Centers Are: Central Ohio and Pike County

Central Ohio, around Columbus and New Albany, hosts most of the state's data center load, and southern Ohio's Pike County is where the largest new campus is planned.

AEP Ohio's own figures show how lopsided it is. Of the 5,642 MW signed under its data center tariff as of February 12, 2026, 4,842 MW is in central Ohio and 800 MW is elsewhere in its territory. That is 86% of the new contracts in one region.

Most of that contracted load was not drawing power in 2023, which is why EPRI's electricity figure lags the building count.

Pike County

The second cluster is a former federal uranium enrichment site, the Portsmouth Gaseous Diffusion Plant in Pike County, now branded the PORTS Technology Campus. On March 20, 2026 the U.S. Department of Energy announced a data center and power project there, with SoftBank's SB Energy building the generation and transmission, including a $4.2 billion grid upgrade in partnership with AEP Ohio.

Energy Secretary Chris Wright said the project would "add power generation, create jobs, and ensure the United States wins the AI race."

We cover the campus in the section on AI data centers below.

More AI infrastructure stories like this

The real hardware, chip, and data center side of AI, explained plainly, every Wednesday and Saturday.

AEP Ohio's 17.9 GW Pipeline Is Twice Its Peak Demand

AEP Ohio has 17,861 MW of data center projects under contract. Of that, 5,642 MW was signed after the new data center tariff took effect and 12,219 MW was signed before it. The figures come from AEP Ohio's February 12, 2026 update to the Public Utilities Commission of Ohio (PUCO), and the projects are scheduled to come online in stages through 2035.

The Number Most Guides Don't Show

AEP Ohio's peak demand across all customers has ranged between roughly 8,000 MW and 10,500 MW in recent years. The 17,861 MW under contract is therefore about 1.7 to 2.2 times the utility's entire peak load. Put against EPRI's 2023 data, which implies Ohio data centers averaged about 270 MW over the year, the contracted load is about 66 times what they drew then.

The pipeline has also shrunk since the rules changed. Before PUCO approved the tariff, data centers and developers had requested about 30,000 MW, and only about 13,023 MW of that paid for a study. That is the clearest sign of what a pay-whether-you-use-it rule does to speculative requests. I treat the 17,861 MW as a ceiling, not a forecast.

The tariff

PUCO approved AEP Ohio's data center tariff in an order dated July 9, 2025. It applies to new or expanded loads above 25 MW. They must pay for at least 85% of their subscribed capacity whether or not they use it, for up to 12 years, and leaving early costs an exit fee equal to three years of minimum charges.

"Today's order represents a well-balanced package that safeguards non-data center customers." (Jenifer French, Chair, Public Utilities Commission of Ohio, Jul 2025)

The industry accepted the principle while fighting the details.

"The data center industry is committed to paying its full cost of service." (Lucas Fykes, Director of Energy Policy, Data Center Coalition, Jul 2025)

For how the same logic is playing out in other states, including Texas's curtailment rules, see our guide to data centers by state.

AEP Ohio Data Center Pipeline vs Its Own Peak Demand (GW)

Ohio data centers, avg load…0.27 GWSigned under new tariff5.64 GWAll-customer peak, high end…10.5 GWTotal contracted17.86 GWRequested before the tariff30 GWSource: AEP Ohio update to PUCO (Feb 12, 2026); EPRI Powering Intelligence (May 2024), derived average load

AEP Ohio peak demand has ranged between about 8 and 10.5 GW in recent years. Contracted projects are scheduled to come online in stages through 2035.

AEP Ohio Data Center Pipeline vs Its Own Peak Demand (GW)
CategoryValueUnit
Ohio data centers, avg load 2023 (EPRI)0.27GW
Signed under new tariff5.64GW
All-customer peak, high end of recent range10.5GW
Total contracted17.86GW
Requested before the tariff30GW

What the Ohio Data Center Tax Break Costs

Ohio's data center sales tax exemption cost the state about $1.57 billion in 2025, up from about $555 million in 2024 and roughly 11 times the state's $136 million forecast, according to Ohio Department of Taxation figures reported in May 2026. The figures cover state revenue only. Local sales tax breaks are extra.

YearCost to the stateNote
2024About $555 millionItself about four times the forecast
2025About $1.57 billionForecast was $136 million

The exemption is discretionary, not automatic: projects apply to the state's Tax Credit Authority. That is why Governor Mike DeWine could stop it quickly. On May 27, 2026 he directed the authority to stop processing new applications while a legislative committee reviews the industry. Projects that were already approved keep their breaks.

The legislature has not settled the question. Lawmakers failed to reach agreement on data center regulations before leaving for recess in June 2026, and repeal bills have been introduced.

Ohio Votes: Local Bans, Moratoriums and the Statewide Push

Ohio is where much of the local backlash is concentrated. On November 3, 2026, 21 of the 41 local data center ballot measures nationwide were in Ohio, spread across 18 municipalities, and bans or limits passed in at least 14 towns, according to media tallies. All the results are unofficial until county boards certify them.

  • Trenton: Issue 17, which limits large data centers, passed with about 79.7% of the vote.
  • Central Ohio: Fortune reported that all five communities with data center measures on the ballot voted against data centers.
  • Grove City: Issue 28, which requires a referendum on large developments that use a lot of water or land, passed with about 55%.

Voters were reacting to things they could see and hear. Residents near existing facilities describe constant low-frequency noise from cooling systems and backup generators, according to a Sierra Club Ohio post, while the Data Center Coalition's Dan Diorio says the industry abides by noise regulations. For the engineering behind that noise, see our explainer on data center cooling.

Local moratoriums are spreading too. The Ohio Newsroom reported around 18 municipalities considering or enacting them, including Lordstown and Athens. A statewide constitutional ban was not on the ballot: backers fell short of the roughly 413,000 valid signatures needed and plan to try again for the 2027 general election, according to reports.

AI Data Centers in Ohio: The 8 GW Pike County Campus

The biggest AI data center planned in Ohio is the PORTS Technology Campus in Pike County, and reports say OpenAI will take about 8 GW of it. On August 17, 2026, OpenAI said it would lease about 8 GW of IT capacity at the site from SB Energy under a 20-year lease, with NVIDIA providing a backstop, according to multiple trade outlets.

Total site power is higher than the IT figure, because cooling and power conversion take their share. The Department of Energy's March 2026 announcement described a campus of up to 10 GW, with up to 10 GW of new generation, including 9.2 GW of natural gas, and $33.3 billion of Japanese funding tied to the gas component. The campus is meant to start at about 4.25 GW, with an option to expand.

Two cautions apply. First, these are announced capacities, not energized ones, and the Department of Energy said only that construction was expected to begin in 2026. Second, plans of this size depend on generation, transmission and financing that still have to be delivered. For how OpenAI's other large sites fit together, see our guide to the OpenAI Stargate project.

The Pike County campus is a different kind of data center from the ones in New Albany. The central Ohio buildings serve cloud customers and sit near the cities they serve. The Pike County site is a power-first campus built on a former industrial site to train and run AI models.

What Comes Next for Ohio

Ohio's next year will be decided by three things: whether the legislature ends the tax break, whether the Pike County campus gets built, and how the new local bans hold up.

  • The tax break. DeWine's pause covers new applications only. Whether lawmakers end, halve or restore the exemption will shape how many of the planned buildings are worth building.
  • The contracts. AEP Ohio's 17,861 MW is scheduled through 2035. Each year a project slips is a year the utility's other customers carry the risk, which is what the 85% minimum is meant to cover.
  • The local bans. Where voters passed limits, projects that need rezoning or water will face a referendum. Where they did not, expect more fights over noise and power lines.

My read is that Ohio will end this cycle with fewer, larger and more conditional data centers than the 278 on today's map. The count will fall, but the megawatts may not.

Frequently Asked Questions

How many data centers are in Ohio?

About 166 were operating in February 2026, according to Pew Research Center's analysis of DataCenterMap, which counted 223 in total including 57 planned or under construction. Cleanview tracks 278 Ohio buildings in all stages as of November 8, 2026. Counts vary with how each tracker treats campuses and planned sites.

Where are most data centers in Ohio?

Central Ohio around Columbus and New Albany. Of the 5,642 MW signed under AEP Ohio's data center tariff as of February 2026, 4,842 MW is in central Ohio. The largest new campus, the PORTS Technology Campus, is in Pike County in southern Ohio.

How much power do Ohio data centers use?

EPRI estimated Ohio data centers used 2.4 TWh in 2023, about 1.58% of the state's electricity, an average draw of roughly 270 MW. AEP Ohio now has 17,861 MW of data center projects under contract, scheduled to come online in stages through 2035, so demand is expected to rise sharply.

What is the AEP Ohio data center tariff?

A rate approved by the Public Utilities Commission of Ohio on July 9, 2025. New or expanded loads above 25 MW must pay for at least 85% of their subscribed capacity whether they use it or not, for up to 12 years, with an exit fee equal to three years of minimum charges if they leave early. It aims to stop other customers paying for unused grid capacity.

How much does the Ohio data center tax break cost?

About $1.57 billion in 2025, up from about $555 million in 2024 and roughly 11 times the state's $136 million forecast, according to Ohio Department of Taxation figures reported in May 2026. Governor DeWine paused new applications on May 27, 2026. Projects already approved keep the break.

Did Ohio voters ban data centers?

In many towns, yes. On November 3, 2026, 21 of the 41 local data center ballot measures nationwide were in Ohio, and bans or limits passed in at least 14 towns, according to unofficial tallies. A statewide constitutional ban was not on the ballot because backers fell short of the signatures needed.

What is the OpenAI data center in Ohio?

A planned campus at the PORTS Technology Campus in Pike County, on the former Portsmouth uranium enrichment site. OpenAI said on August 17, 2026 that it would lease about 8 GW of IT capacity from SB Energy under a 20-year lease. The Department of Energy described a site of up to 10 GW with new gas generation. It is announced, not built.

Is Ohio stopping new data centers?

Not statewide. DeWine paused new tax-break applications in May 2026, and about 18 Ohio municipalities have considered or adopted moratoriums. Utilities can still sign contracts under the AEP Ohio tariff, and projects with existing approvals continue.